Tier-1 Automotive Manufacturer Phase-II 220kW

Tier-1 Automotive Manufacturer at Bawal added capacity to the existing solar (phase-1) with an additional 220kw(phase-2). After the phenomenal success of phase-1 the client not only increased its capacity but also recognized Winnerspitch Energy for its quality work.

This project is unique as automated sprinkler system for panel cleaning is used.The 220kW project generates around 1000 units per day. More than 700kg of coal would have been burnt to produce the same amount of electricity. Payback period of project is around 3.4yr.

Result


Savings of approx INR 40lakhs per year